top of page
3 & Before.jpg

BEFORE

7 & After.jpg

AFTER

Concrete Water Tank Reline Bath

Reline of a Concrete Water Tank at a Major University in the South West

Guarantee_edited.png

Project Brief

A major university in the southwest was facing serious problems with its water storage infrastructure. A structural assessment revealed extensive deterioration of the internal concrete surfaces of its two large holding tanks. Corroded sparge pipes and passing outlet valves added to the risk, threatening the reliability of the water supply across campus.

Replacing the tanks entirely would have involved significant cost and logistical disruption, particularly given their size and location. With no bypass systems in place, the university needed a solution that could be delivered with minimal downtime — and without exceeding budget. Titan was called in to assess, advise, and deliver a long-term, cost-effective solution.

Solution

Our engineers designed and delivered a carefully phased programme of works to bring the tanks back into full service — without any disruption to supply.

  • Preliminary Repairs: The passing outlet valves were replaced before any lining works began. This enabled the tanks to be worked on in sequence without interrupting the university’s water supply.

  • Internal Reline Using Polyurethane: A WRAS-approved polyurethane lining was applied to the internal surfaces of each tank. This product delivers a tough, seamless, and flexible finish designed to protect concrete structures long term. The lining offers 35% elasticity to tolerate structural movement — ideal for older tanks with historical settlement or wear.

  • Upgrades to Tank Components: New sparge pipes were installed to replace the corroded units and ensure even water distribution, in line with modern standards.

  • Fully Managed Delivery: The entire programme was handled by our in-house engineers, from planning and compliance checks through to commissioning and sign-off.

Key Benefits Delivered

 

  • Major Cost Savings: The university saved over £100,000 compared to the likely cost of tank replacement — without compromising safety or performance.

  • Zero Disruption: By working in sequence and upgrading critical components first, the university’s water supply was maintained throughout the works.

  • 10-Year Guarantee: The client gained peace of mind with our comprehensive guarantee covering both product and workmanship.

  • Regulatory Compliance Restored: All remedial works brought the tanks in line with current water hygiene regulations.

Don’t Replace - Reline

 

Looking to extend the life of your concrete tanks without major costs or downtime? Visit our Water Tank Relining page to learn how we can help. Or, to see more of our recent tank reline projects, visit our page:​​

Project Gallery

CLIENT FEEDBACK

"Engaged Titan Mechanical for this project, and we didn’t regret it. The works included the full reline of our two large concrete holding tanks, as well as some valve replacements. From initial request to completion. Titan provided a professional service - Would highly recommend."

Alan Benzie, Estates Manager

  • Facebook
  • LinkedIn
  • Instagram
  • YouTube

Learning Centre

Visit our learning centre to explore a treasure trove of useful articles filled with content designed specifically for commercial facilities managers.

Get in Touch - Let's Make Some Memories

Titan Mechanical Services

Get In Touch

Unit 102 Merlin Park
Ringtail Road
Burscough, Lancashire
L40 8JY

Northern Office

01704 335800

Southern Office 

02080 599651

Take A Look At Our Other Brands!

Water Tank Replacement
Tank Reline

Follow Us on Social!

  • Facebook
  • LinkedIn
  • Instagram
  • YouTube
bottom of page